Sunday 20 December 2015

Work and Time

                                      Work &Time,
                       

Work and Time
In most of the problems based on Work and Time, either the amount of time taken to finish a given job or the amount of work done is to be calculated. Unless otherwise specified, the amount of work done is generally taken as unity (1). Also, if it is given that a person X can finish a job in D days, then it implies that X alone can do the job in D days.

·          If a man can do a piece of work in N days (or hours or any other unit of time), then the work done by him in one day will be 1/N of the total work.
El. Animesh can finish a piece of work by himself in 14 days. Then calculate the amount of work done by him in 1 day and 11 days.
Sol. The amount of work done by Animesh, working alone in 14 days = 1 unit of work.
So, the amount of work done by Animesh, working alone in 1 day = 1/14 unit of work and in 11 days = 11/14 units of work.
·          If A is twice as good a workman as B, then A will take half the time B takes to finish a piece of work.
 E2. Suresh can finish a piece of work by himself in 42 days. Mahesh, who is 1/5 times more efficient as Suresh, requires X days to finish the work by working all by himself. Then what is the value of X?
Sol. Suresh, working alone 42 days = 1 unit of work.
Mahesh is 1/5 times more efficient than Suresh. So Mahesh is 6/5 times as efficient as Suresh. Hence Mahesh should
require 5/6th of the time, the time taken by Suresh.
Therefore time taken by Mahesh = 5/6 x 42 = 35 days.

Measurement of work
Work can be measured by many units. Some of them are
 Man-days
A certain number of men working for a certain number of days.
For example, 5 men can finish a piece of work in 13 days, This implies that the work is of 5 x 13 = 65 Man-days, i.e., if one man alone works to finish the given work then he is going to take 65 days to finish it and if 65 men work together, then the work would be finished in 1 day.
Man-hours
A certain number of men working for a certain number of hours.
For example, 3 men can finish a piece of work in 13 hours. This implies that the work is of 3 x 13 = 39 Man-hours, i.e., if one man alone works to finish the given work then he is going to take 39 hours to finish it and if 39 men work together, then the work would be finished in 1 hour.
Some others are, Man-minutes, Machine-hours etc.

E3. 4 men of equal efficiencies can finish a piece of work by working 10 hrs a day in 7 days. How many men will be required to finish the same work if they work 3.5 hrs a day and the work is to be completed in 10 days?

     Sol. The total work to be done = 4 x 10 x 7 = 280 man hours Let X men be required to finish this job, then
280 = X x 3.5 x 10 .so, X = 8. So, 8 men are required.
If A and B can do a piece of work in X & Y days respectively while working alone, they will together take X x Y/X + Y days to complete it.

It can be explained as follows:

A's one day work = 1/X , B's one day work = 1/Y
(A + B)'s total one day work = 1/X + 1/Y of the total.
Let the total work be 1 (unity). Now1/ X+1/Y of 1 can be finished in one day.
Total work can be finished in      1 /  1/X + 1/Y   =        X x Y / X+Ydays.            
E4. A can finish a piece of work by working alone in 12 days. B while working alone, can finish the same work in 24 days. If both of them work together, then in how many days, the work will be finished?
Sol. Applying formula, 12 x 24/ (12 + 24) =   288/ 36 = 8.
                              
The work will be finished in 8 days.
If A, B, C can do a piece of work in X, Y, Z days respectively while working alone, they will together take XxYxZ / XxY+YxZ+ZxX days to finish it.

It can be explained as follows:
                                           
A's one day work =1/X , B's one day work = 1/Y and C's one day work = 1/Z .
Their total one day work = 1/X + 1/Y + 1/Z of the total work.
Let the total work be 1 (unity).
Now 1/X +1/ Y +1/ Z of 1 can be finished in one day
Total work can be finished in     
            1                =                      XxYxZ               days.
1/X+1/Y+1/Z          XxY+YxZ+ZxX X+Y+Z

E5. Ganpat , yogesh , bhagwat can do job in 15, 20 and 30 days respectively. In how many days can the job be finished if they work together?
Sol. Ganpat's 1 day work = 1/15 of the total. Yogesh's 1 day work = 1/20 of the total. Bhagwat's 1 day work = 1/30 of the total.
They can do (1/15+1/20+1/30) of the total work in 1 day. Total work can be finished in
= 20/3 days.
E6. A and B require 10 days to complete a job. B and C require 12 days to complete the same job. A and C require 15 days to complete the same job. Find the number of days required, if all are at work, to complete the same job.

Sol. A+B= 1/10 , B+C= 1/12 and C+A= 1/15
2(A+B+C)= 1/10+1/12+1/15   6 + 5 + 4  =  15/60 = 1/4  
                                                       60
A + B + C = 1/8.
Hence if A, B and C all work together, they will need total 8 days to complete the work.

If A, B and C can finish a piece of work in X, Y and Z days respectively, while working alone and together they require M days to finish the work, then the amount of work done by A is M/X, B is M/Y and C is M/Z.
Applying the concept of variation
Most of the questions given in this chapter can be solved using the concept of variation. The following points should be kept in mind while solving the questions by this method.
→Number of persons employed to do the work is directly proportional to the amount of work done. (More the number of persons employed, more the work done)
E7. 4 men take 3 days to paint a wall. If 20 men with same efficiencies are working, then how many walls can be painted in 3 days?
Sol. Since 4 men can paint the wall in three days, so 20 men can paint 20/4 i.e. 5 such walls in 3 days.

The number of days is directly proportional to the work done. (More the number of days for which a work was done, more shall be the total amount of work done)

E8. A man takes 3 days to paint a wall. If he works for 12 days,  then how many walls can be painted by him?
     
 Sol. Since in 3 days he can paint the wall, so in 12 days, he can paint 12/3 i.e. 4 such walls. The number of persons employed is inversely proportional to the number of days reciuir~d to finish a work. (More the number of persons employed, less will be the time required to finish the work)
E9. A man takes 5 days to complete a job. If he is assisted by 4 of his friends of same efficiency, then in how many days can the job be completed?
Sol. Since the man takes 5 days to complete the job, the job is of 5 man — days. When he is assisted by 4 of his friends, they can do the job (5 man — days) in one day.
E10.If 12 men can build a wall 100 m long, 3 m high and 0.5 m thick in 25 days. In how many days will 20 men build a wall 60 m long, 4 m high and 0;25 m thick?
Sol.                    Man        Days      Length       Height        Thickness
           12    25    100       3       0.5
                           20           X          60                4               0.25 

25    =    20    x   100    x 3   x       0.50
X          12        60      4           0.25
X=6.
The concepts used to solve this question are
Men and days are inversely proportional to each other.
Length, height and thickness of the wall are directly proportional to the number of days required.
   E11.A contractor undertook to do a certain work in 75 days and employed 60 men to do it. After 25 days he found that only 1/4th of the work was done. How many more men must be employed so that the work may be finished in time?
Sol. 60 men in 25 days can do 1/4 of work. For 3/4th of work in 50 days,
men required=60 x (3/2) = 90.
Additional men = 90 — 60 = 30.

Some important formulae
ü  Two persons A and B, working together, can finish a piece of work in M days. If A can finish the job in X days by working alone, then B will finish the job by working alone in M x X / X - M days.

E12. Ram and Shyam working together can finish a work in 12 days. If Ram alone can do the same in 20 days, then in how days, Shyam alone can complete the work?

Sol. Let Shyam take x days to complete the work.
Work done by both in 1 day =  1/20 + 1/X

Number of days required = 20 x X = 12 (given)
                                  20+X

=20x-12x= 240=x=30.
So Shyam alone can do the work in 30 days.
Short-cut: Using formula we can get the answer as
12 x 20/ 20-12= 30 days
 If A can complete a/b part of a work in X days, then c/d  part of the work will be done in               
b x c x  X  /a x d    days.
E13.If A can complete a work in 16 days, then in how many days can he complete 3/4 th of the work?

Sol. Using formula we get 1/1 x 3/4 x 16 = 12 days.
       If A can finish a work in X days and B is K times as efficient as A, then the time required by both A and B working together to finish the job will be X/1+k days.
E14.Mayank can finish a work in 10 days. Mahesh is 2 times as efficient as Mayank. If they work together, in how many days will the work be finished?

Sol. Time Tken by mayank to do the work = 10days

.•. Time taken by Mahesh to do the work = 5 days. (He is twice as efficient)

1 day's work = 1/10 +1/5 = 3/10

Time required to complete the job = 10/3 days.

Short-cut: Using formula, we can get the answer as
     10        =  10 days.
  1+2        3                                                                          
A is K times as good a worker as B and takes X days less than B to finish the work. Then the amount of time required
by A and B working together is k x X / k2 - 1days.

E15. Ram is three times as good a worker as Rahim and takes 8 days less than Rahim to finish the work. Find the amount of time required by Ram and Rahim working together, to do the work.

Sol. Let Rahim take x days to complete the work and so Ram takes x — 8 days =x/3 days (Ram is 3 times efficient).
So, x = 12 and so x - 8 = 4.
Time required to complete the work, working together

=                1
           1/12 + ¼      =    12/4   = 3days
Short-cut: Using formula we get = 3 X 8 / 32 - 1= 3 days.
Concept of WORK EQUIVALENCE
In order to solve certain types of questions, there is a very logical method that can be used. This is the WORK EQUIVALENCE method which works on a simple premise — make the LHS equal to the RHS on the basis of SAME UNITS in terms of which work can be measured.
Let's take some examples.
E16.A group of soldiers can completely destroy an enemy bunker in 7 days. However 12 soldiers fell ill. The remaining now can do the job in 10 days. Find the original group strength.
Sol. Here, first of all, let us see how WORK can be defined. It is obvious that work can be measured as "destruction of the enemy bunkers."
In the first case, let us say that there were S number of soldiers in the group. So they had to work for 7 days for the work which we call W.
      Sx7=W      ...(1)
Now 12 fell ill and the remaining did the work in 10 days. Hence the new equation is
(S-12)x10=W       ...(2)
Just compare the two equations to get the answer
S x 7 = (S - 12) x 10 =7S=10S-120 =120=3S

= S = 40 soldiers.
Hence, there were 40 soldiers in the group initially.

E17.A group of 20 cows can graze a field 3 acres in size in 10 days. How many cows can graze a field twice as large in 8 days?


Sol. Here, first of all, let us see how WORK can be defined. It is obvious that work can be measured as "acres grazed." In the first case, there were 20 cows in the group.
They had to work for 10 days to do the work which we call W (which = 3).
20x10=3   ...(1)
Do not be worried about the numerical values on either side. The point is that logically this equation is consistent as the LHS indicates "Cowdays" and the RHS indicates "Acres'; both of which are correct ways of measuring work done.
      Now the field is twice as large. Hence the new equation is
      = Cx8=6         ...(2)
      Just divide (2) by (1) to get the answer.
8C / 200 = 6 / 3
8C=2x200
C = 400/ 8 = 50 cows.
       Hence, there were 50 cows in the second group.
                      3/4    1/2
The expression for emptying pipe which can empty el part of cistern in tl min and e2 part in t2 min is tl /el = t2/e2.    
E25.An empty pipe can empty 5/6 of the cistern in 20 min. What part of the cistern will be emptied in 9 min?

Sol. Using the formula,
 t1 = t2 = 20  =  9  = e2  = 3
e1   e2   5/6     e2           8
in 9 min, 3/8 part of the cistern will be emptied
If two pipes A and B are opened for different time periods, then to solve the questions we use
A's amount of work + B's amount of work = 1.
A's open time        +               B's open time          =1
Alone fill time of A                              Alone fill time for B
E26.Two pipes A and B can fill a cistern in 10 and 15 min respectively. Both pipes are opened together but at the end of 3 min, 'B' is turned off. How much time will the cistern take to fill?

Sol. Let the cistern be filled in T min.
.•. Pipe A is opened for T min and pipe B is opened for 3 min. Using the formula, for filling the cistern,
A's amount of work + B's amount of work = 1.
T/10 + 3/15 = 1 ,  T = 10 (1 – 1/5)  = 8.
The cistern is filled in 8 min.
E27.Two fill pipes A and B can fill a cistern in 12 and 16 min respectively. Both 'fill pipes' are opened together but 4 min before the cistern is full, one pipe A is closed. How much time will the cistern take to fill?
Sol. Let the cistern be filled in T min.
.•. Pipe B is opened for T min and pipe A is opened for (T- 4) min.
Using the formula, for filling the cistern
A's amount of work + B's amount of work = 1.

A's open time   +   B's open time             =1
Alone fill time of A       Alone fill time for B

                                      
The cistern is filled in 91/7 min.


No comments:

Post a Comment